Author Topic: Large portions of Access to Vedder river will be closed during prime Coho Season  (Read 20971 times)

Roderick

  • Sr. Member
  • ****
  • Offline Offline
  • Posts: 206

Don't forget insurance. That's never cheap, and they can't work without it.
Logged
You shoulda been here yesterday.

Cyanescens

  • Jr. Member
  • **
  • Offline Offline
  • Posts: 39

you could be right but there will also be Engineering, Environmental, Security & Administrative costs associated with the work; possibly more (such as a contingency). Often all the other stuff costs more than the actual work of digging and removal. These contracts are usually posted and your MLA could likely get the break down.

I had a look at the Jake's website and in the past they have dug all this stuff out without actually working in the river bed. They dig it out and leave a barrier between the pit and the river and then open a channel. This produces the big frog water holes coho love. I assume work has started. I drove over the Canal at the #1 Saturday. The river was love and clear.

Engineering, environmental monitoring, and contingency arent usually included in the contractor's scope so wouldnt be included in the $13M. Administrative cost and insurance are included in the $250/hr force account rate I mentioned.

Most likely this contract could only be awarded to a contractor with approval from FN and its possible they only approved of Jakes. They knew that and took advantage.
Logged

RalphH

  • Old Timer
  • *****
  • Offline Offline
  • Posts: 5006
    • Initating Salmon Fry

Engineering, environmental monitoring, and contingency arent usually included in the contractor's scope so wouldnt be included in the $13M. Administrative cost and insurance are included in the $250/hr force account rate I mentioned.

Most likely this contract could only be awarded to a contractor with approval from FN and its possible they only approved of Jakes. They knew that and took advantage.

you are discounting the fact there could be more than 1 contractor. The project is budgeted at 13 million. The Province will have to get engineering and environmental if a general contractor doesn't provide it.
« Last Edit: September 10, 2024, 09:26:12 PM by RalphH »
Logged